Re-roof

 Conditions of Permit for Re-roof (Tear-off)

 

(1) Minimum 15-pound felt paper on roof

(2) Ice dam protection shall be installed from the edge of the roof to a point not less than 24” from inside the exterior wall line of the building.  Ice dam protection shall have a separate inspection.

(3) Valley protection required

(4) Drip edge at the roof edge or rake required on all asphalt shingles

(5) Attic ventilation shall be checked for the correct number of vents (1:150)

(6) A cricket or saddle shall be installed on the ridge side of a chimney or penetration 30” wide perpendicular to the slope.

 

Required inspections: 

(1) Ice & Water (several inspections may be required based on size of roof)

(2) Final inspection

 

ALL PERMITS:
  1. A Long Grove Building Department approved set of construction documents must be on-site available for inspections. {Section:  2015 International Residential Code R106.3.1}

  2. All construction shall comply with the Village of Long Grove codes, amendments, and ordinances.
  3. All debris, including dumpster, shall be removed from site prior to a final.
  4. Final site shall be stabilized with topsoil, seed and erosion control blanket or sod prior to a final (where applicable).
  5. CONSTRUCTION HOURS:  Monday through Friday 7:00 a.m. to 7:00 p.m. , Saturday 8:00 a.m. to 5:00 p.m.  Construction on Sunday permitted only by an occupant on own residence 10:00 a.m. to 5:00 p.m. {Ordinance No. 2003-O-26}.